LTA application for NTPC's 1,320 MW Tanda power project awaited

The LTA application from NTPC for it's 1,320 MW Tanda power project in Uttar Pradesh is yet to be received, according to Powergrid.

 

The power major, which has already applied for connectivity of its Tanda project, requires the same by December, 2016.

Connectivity could be provided through 2x135 MVA, 400/220 kV integrated current transformer at Tanda to connect the proposed generation at 400 kV with the existing 220 kV bus. The ICTs at Tanda would provide required connectivity to the grid.

It is only after the said application is received, that revised system studies for power evacuation would be carried out based on information like beneficiary, quantum and revised network configuration, etc.

The connectivity may be granted through the said ICT at Tanda subject to provision of 1x125 MVA reactor at the generating station, separate LTA applications for evacuation of power to different beneficiaries and other applicable conditions.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!