Indonesia to shut down 18 power plants during Idul Fitri

PLN will shut down 18 power plants supplying 7,200 megawatts of power to Java and Bali during the Idul Fitri holiday.

 

“The electricity needs on Aug. 17 and throughout the Lebaran [Idul fitri] holiday will decline, thus our need to adjust the supply,” said PLN president director Nur Pamudji.

Java and Bali regularly need 19,135 megawatts of electricity during daylight hours and 20,424 megawatts at night, Nur said. The PLN’s Java-Bali capacity, meanwhile, reaches 27,670 megawatts.

On Independence Day on August 17, demand is expected to drop to 15,000 megawatts. During Idul Fitri, it will decline to 13,000 megawatts.

Nur said PLN would turn off the power plants in stages, adding that some have already been turned off.

PLN will restart the power plants on Aug. 27.

For more.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!