, Philippines

AboitizPower's 6-MW Binary Plant successfully restored

Restoration took over a year.

AboitizPower presented its 6-MW Binary Plant at the Makiling-Banahaw Geothermal Project last April 27.

The Binary Plant 1 utilizes excess heat from spent brine to generate clean and renewable energy for the Luzon Grid. At MakBan, the water in the reservoir that is not hot enough is fed into the Binary Plant to still generate electricity.

The Binary Plant 1 became operational in the second half of 2016 after the completion of restoration work.

“It took us more than a year to complete the restoration, but we were able to add 6 MW installed capacity of renewable energy to our facility, utilizing heat from geothermal byproducts and idle equipment,” APRI President and COO Felino Bernardo said.

The Binary Plant 1 is one of three binary cycle power plants in the MakBan Geothermal Project Complex. The binary cycle plants were decommissioned in 2008. Of the three, only Binary 1 was found viable for rehabilitation.

Join Asian Power community
Since you're here...

...there are many ways you can work with us to advertise your company and connect to your customers. Our team can help you dight and create an advertising campaign, in print and digital, on this website and in print magazine.

We can also organize a real life or digital event for you and find thought leader speakers as well as industry leaders, who could be your potential partners, to join the event. We also run some awards programmes which give you an opportunity to be recognized for your achievements during the year and you can join this as a participant or a sponsor.

Let us help you drive your business forward with a good partnership!