NLC invites bids for steam generator & auxiliaries package for 1,000 MW Neyveli New TPP
Neyveli Lignite Corporation (NLC) has invited bids for the "Steam Generator & Auxiliaries Package (NTA1)" for
the 1,000 MW Neyveli New Thermal Power Project in Tamil Nadu.
The scope of work includes design, engineering, manufacture, supply, inspection, all mechanical, C&I systems,
electrical equipment and systems, steel structures, civil works, insurance, erection, testing, commissioning
and performance guarantee testing, guarantee and warranty for two lignite fired steam generators and
auxiliaries for the 2x500 MW plant.
As per the eligibility criteria, a bidder should have designed, manufactured, supplied, erected and
commissioned (or supervised erection and commissioning of) at least one pulverized lignite fired steam
generator of 500 MW capacity or above.
The time schedule for the completion of trial operation and performance guarantee tests of the plant and
equipment is as follows:
Completion of Trial Operation
Unit 1 Steam Generator -- Within 48 months from the date of LoA
Unit 2 Steam Generator -- Within 54 months from the date of LoA
Completion of Performance Guarantee Test
Unit 1 Steam Generator -- Within 51 months from the date of LoA
Unit 2 Steam Generator -- Within 57 months from the date of LoA
The last date for bid submission is November 17, 2012.